PM1 Lesson 1.03 (Organizations)
Presentation
•
Business
•
9th - 12th Grade
•
Practice Problem
•
Medium
Bobbie Jones
Used 7+ times
FREE Resource
16 Slides • 11 Questions
1
Enterprise Environmental Factors
▪Internal and external environmental
factors that surround or influence a
project’s success.
▪Considered as inputs to most planning
processes.
▪Often abbreviated as “EEFs”
2
Enterprise Environmental
Factors Examples:
External
▪Government regulation
▪Market conditions
▪Infrastructure
▪External political conditions
Internal
▪Organizational culture
▪Type of organizational
structure
▪Internal political conditions
▪Available resources
3
Multiple Choice
If a project manager of a construction job has halted project due to a shortage in local lumber supply, this lumber shortage impacts the success of her project. What is this called?
business needs
enterprise environment factors
a project management plan
a project statement of work
4
Multiple Choice
What is the term we use to discribe project difficulties that arise out of home owner associations' regulations on the neighborhood where we need to build a house?
Internal Enterprise Environmental Factor
External Enterprise Environmental Factor
Projectized Organizational Structure Issue
Functional Organizational Structure Issue
5
Stakeholder
identification
CS11 1.03 Project Stakeholder Identification
6
What is a
Stakeholder?
▪ Stakeholders are persons or organizations who are actively
involved in the project or whose interest may be positively or
negatively affected by the performance or completion of the
project.
▪ In general, stakeholders and their interests should be identified
and involved/addressed as early in the process of the
development of the project as possible.
▪ Projects are undertaken to fulfill the requirements of
stakeholders.
▪ Project success is measure by the satisfaction of the project’s
stakeholders
7
Stakeholder Identification
▪ Examples of project stakeholders may include:
▪ Project Sponsor
▪ Higher Management
▪ Project Team Member
▪ Stakeholder Identification is continuous
▪ Occurs ongoing until project ends
▪ New may be added
▪ Some may lose interest
▪ Power and influence may also change over time
8
Identify
stakeholders by:
▪ Brainstorming.
▪ Collecting categories and names from
informants in the community.
▪ Interviews
▪ Consulting with organizations that either are
or have been involved in similar projects, or
that work with the population or in the area of
concern.
▪ Expert Judgement
▪ Getting more ideas from stakeholders as you
identify them.
▪ If appropriate, advertising.
9
Stakeholder Categories
Primary stakeholders:
• Beneficiaries or targets
of the project.
Secondary stakeholders:
• Those directly involved
with or responsible for
beneficiaries or targets
of the project.
• Those whose jobs or
lives might be affected
by the process or
results of the project.
Key stakeholders:
• Government officials
and policy makers.
• Those who can
influence others.
• Those with an interest
in the outcome of an
project.
10
Successful Projects
▪Result from:
▪Careful Planning
▪Talent & Collaboration of a Project Team
11
Multiple Choice
The stakeholders have the most influence on any project at which stage?
Planning
Execution
Closing
Initiation
Monitoring and Controlling
12
Reorder
Place the Order of the project life cycle stages in order
Initiation
Planning
Execution
Monitoring and Controlling
Closing
13
Project
Management
Organizational
Structures
CS11 1.04 Project Management’s Role in the
Corporate Environment
14
Introduction
▪What is an Organizational Structure?
▪Types of Organizational Structures:
▪ Functional
▪ Matrix
▪ Weak
▪ Balanced
▪ Strong
▪ Projectized
▪ Composite - No Longer A THING!
15
Functional
16
Matrix Organizations
▪Blends of functional and projectized
characteristics.
17
Weak Matrix
18
Balanced Matrix
19
Strong Matrix
20
Projectized
21
Multiple Choice
The organizational structure in which the project manager has the greatest amount of authority is a:
composite organization.
functional organization.
matrix organization.
projectized organization.
22
Multiple Choice
A project manager is full time and has their own staff year round, which type of organization do they work with?
composite organization.
functional organization.
matrix organization.
projectized organization.
23
Multiple Choice
A project manager is part-time and borrow from departments when a project is in session, which type of organization do they work with?
composite organization.
functional organization.
matrix organization.
projectized organization.
24
Multiple Choice
In which type of organization would a project manager choose to work if they did not want to control the finances and did not want to take authority over employees?
composite organization.
functional organization.
matrix organization.
projectized organization.
25
Multiple Choice
Which organization type has 3 levels of strength and allows money managment and staff management depending on the level?
composite organization.
functional organization.
matrix organization.
projectized organization.
26
Multiple Choice
In which organization structure does the project management not work for the company on site?
composite organization.
functional organization.
matrix organization.
projectized organization.
27
Multiple Choice
In which organization type does a project manager have the least amount of authority?
composite organization.
functional organization.
matrix organization.
projectized organization.
Enterprise Environmental Factors
▪Internal and external environmental
factors that surround or influence a
project’s success.
▪Considered as inputs to most planning
processes.
▪Often abbreviated as “EEFs”
Show answer
Auto Play
Slide 1 / 27
SLIDE
Similar Resources on Wayground
21 questions
Animation Workflow
Presentation
•
9th - 12th Grade
17 questions
Ratio Analysis
Presentation
•
9th - 12th Grade
21 questions
Cause and Effect
Presentation
•
9th - 12th Grade
20 questions
Sejarah Internet
Presentation
•
9th - 12th Grade
21 questions
Exam Lesson 1 Turtle Programming
Presentation
•
9th - 12th Grade
21 questions
The Brain & Addiction
Presentation
•
9th - 12th Grade
21 questions
EPF Welcome Presentation
Presentation
•
9th - 12th Grade
21 questions
Sewing Pattern Envelope
Presentation
•
8th - 12th Grade
Popular Resources on Wayground
10 questions
HCS SCI 03 Summer School Review 4
Quiz
•
3rd Grade
11 questions
HSMS - Standard Response Protocol
Quiz
•
6th - 8th Grade
16 questions
1.1-1.2 Quiz Review
Quiz
•
9th - 12th Grade
12 questions
Exponent Expressions
Quiz
•
6th Grade
20 questions
Adding and Subtracting Integers
Quiz
•
6th - 7th Grade
11 questions
Northeast States
Quiz
•
3rd - 4th Grade
10 questions
Characterization
Quiz
•
3rd - 7th Grade
10 questions
Common Denominators
Quiz
•
5th Grade