[ITAL] Critical Path Analysis

[ITAL] Critical Path Analysis

Assessment

Presentation

•

Computers

•

12th Grade

•

Practice Problem

•

Medium

Created by

Andy tsui

Used 6+ times

FREE Resource

9 Slides • 6 Questions

1

[ITAL] Critical Path Analysis

Slide image

2

Objectives

  • describe, interpret and create a critical path analysisdescribe, interpret and create a Gantt chart

3

What is CPA?

  • Finds a project's critical path

  • Critical path identifies tasks that must complete on time in order for the whole project to be on time

  • Also defines the minimum amount of time a project can be completed

4

Identifies tasks in Making Bubble Tea

Tasks and how long they takes

5

construct CPA for bubble tea


6

Total length of critical path

  • Adding all time of sequential tasks, plus longest branch of parallel tasks

7

Slide image

Interpret a CPA (Task in P.237)

8

Fill in the Blanks

media image

Identify the longest task

Type answer...

9

Fill in the Blanks

media image

How many milestones are there

Type answer...

10

Multiple Select

Question image

Which tasks are dependent upon bricks being laid?

1

plumbing

2

install windows

3

erect roof

4

lay foundations

11

Multiple Select

Question image

Which tasks can run parallel to install windows?

1

plumbing

2

tile roof

3

erect roof

4

1st fix electrics

12

Fill in the Blanks

media image

How many days is the critical path?

Type answer...

13

Open Ended

Question image

Which tasks form the critical path?

14

To construct CPA, you need....

  • List of tasks

  • How long each task is needed

  • Which tasks are dependent upon predecessors

15

Construct CPA (Example)

p. 238

pattern-tertiary

[ITAL] Critical Path Analysis