Programming- Test #2
Authored by Taylor Short
History
University
Used 1+ times

AI Actions
Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...
Content View
Student View
10 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Project planning is the ______and analysis which results in a built infrastructure requirement
Strategy
Planning
Programming
2.
MULTIPLE SELECT QUESTION
45 sec • 1 pt
Programming requires acquiring __________ to accomplish the planned work.
justification
resources
authority
funding
3.
MULTIPLE SELECT QUESTION
45 sec • 1 pt
Real Property Installed Requirement must meet what two requirements?
Affixed to the building
Used in a facility
Integral part of the facility
Used by Civil Engineering Squadron
4.
MULTIPLE SELECT QUESTION
45 sec • 1 pt
Which of the projects would be considered a facility project?
Installing security cameras in Dorms
Replacing computer is auditorium
Building new dorms
Renovating on-base fitness facility
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
True of False:
You can phase facility projects if each phase is complete and usable.
True
False
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which is NOT a part of the planning phase of the programming process
Identify requirements
Develop Scope
Develop Cost
Classify Work
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which is the first activity in the Programming phase of the Programming Process?
Determine Funding Source
Classify Work
Select Program Avenue
Develop Cost
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?