1.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
What is the difference between a lessons learned register and a lessons learned repository?
The two terms mean the same thing.
The register applies to a single project, and the repository applies to many projects.
The repository applies to a single project, and the register applies to many projects.
The register contains only areas that need improvement in future projects, and the repository contains areas of improvement as well as positive findings.
2.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
In which of the following situations would you not perform the Close Project or Phase process?
When a project is terminated
When a project phase is complete
When a customer validates interim deliverables
When a project is complete
3.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
A team member asks where to find a set of building codes. Which type of knowledge is this?
Implicit
Explicit
Tacit
General
4.
MULTIPLE SELECT QUESTION
45 sec • 1 pt
Which three activities are required for contract closeout? (Choose three.)
To arrange for final settlement of seller payments and claims
To verify work was done and delivered to specification
To provide performance evaluation of seller staff
To update contract artifacts
5.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
When can a contract closeout occur?
Only at the end of the project
Whenever the contract has been completed and accepted
Only at the end of a project, unless the project is terminated early
Whenever a seller is selected
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Microsoft
or continue with
%20(1).png)
Apple
Others
Already have an account?