
Hazards, Risk assessments & Method statements
Authored by Alexandru Pavel
Other
12th Grade
Used 48+ times

AI Actions
Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...
Content View
Student View
18 questions
Show all answers
1.
REORDER QUESTION
1 min • 1 pt
There are 5 stages to the risk assessment. Arrange them in order.
Evaluate the risks
Review your assessment and revise if necessary
Decide who can be harmed and how
Look for hazards
Record your findings
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Doing a .... ............. means examining the workplace to identify areas of risk and minimising those risks and risk of injury. It is the process of recognising what could cause harm to people and decide whether sufficient precautions have been taken to prevent that harm.
action plan
risk assessment
risk assembly
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A ...... is any source of potential damage, harm or adverse health effects on something or someone.
hazard
method statement
danger
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A ....... ......... is a type of health and safety document that people usually use for high-risk work. It describes the steps that workers must take to carry out a particular job safely.
risk assessment
method statement
hazard book
5.
MULTIPLE SELECT QUESTION
45 sec • 1 pt
Which ones can be considered hazards?
Movement of heavy loads
Poor lighting
Falling objects
Extreme weather conditions
Dangerous substances
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
RAMS stands for:
Risk Avoidance Method Statement
Risk Aversion Method Statement
Risk Assessment Method Statement
Risk Amendment Method Statement
7.
MULTIPLE SELECT QUESTION
45 sec • 1 pt
A risk assessment :
Is done by the employee
Is mandatory in a workplace
Is done by the employer
Is an official document
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Microsoft
or continue with
%20(1).png)
Apple
Others
Already have an account?