Critical Path Method (CPM)

Authored by Nguyen Thi Vu Ha

Professional Development

University

Used 28+ times

Critical Path Method (CPM)
AI

AI Actions

Add similar questions

Adjust reading levels

Convert to real-world scenario

Translate activity

More...

13 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

What is critical path method (CPM)

a step-by-step project management technique for process planning that defines critical and non-critical tasks
a graphical display of project activities that helps the users understand the relationships among the activities.
a project management tool to illustrate how the project will run.
A graphical colourful displayed graph

2.

MULTIPLE SELECT QUESTION

20 sec • 1 pt

It determines the earliest time each activity can start and finish and determines the total duration of the project.

Forward Pass

Backward Pass

Side Pass

Critical Path

3.

MULTIPLE SELECT QUESTION

20 sec • 1 pt

It determines the latest time each activity can start and finish without delaying completion of project. It also helps determine the activities that can be delayed or not.

Forward Pass

Backward Pass

Side Pass

Critical Path

4.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

What is CPM?

critical process method

critical path activity

Critical path method

critical process activity

5.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

Critical path in network gives ___ to complete the project.

Critical time

Longest time

Shortest time

Production time

6.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

In Critical Path Method, the project completion period is the EF of last activities.

True

False

7.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

Changing the duration of a critical activity will not affect the overall completion time.

True

False

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Microsoft

Continue with Microsoft

or continue with

Facebook

Facebook

Apple

Apple

Others

Others

By signing up, you agree to our Terms of Service & Privacy Policy

Already have an account?