Chapter 8 - Resourcing Projects
Authored by Aaron Pook
Business
University
Used 12+ times

AI Actions
Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...
Content View
Student View
12 questions
Show all answers
1.
MULTIPLE SELECT QUESTION
1 min • 1 pt
What are the two types of abilities needed when resourcing projects?
Research ability
Technical ability
Analysis ability
Behavioral ability
2.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Below are the actions to reduce the critical path, EXCEPT:
Reduce the project scope and/or quality
Overlap sequential activities
Decrease the number of work hours/days
Schedule activities at the same time
3.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Estimate Activity Resources focuses exclusively upon the identification of the number of human resources required to perform each scheduled activity.
True
False
4.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
When recruiting resources to support a project, it is helpful to bring core team members and key subject matter experts on board as early as possible, to help plan the project and develop the project culture.
True
False
5.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
When resource overloads are extreme, project managers may need to consider the acquisition of additional resources, reductions in scope or extensions to the project schedule.
True
False
6.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
When constructing a responsibility matrix or “RACI” chart, it is important to ensure that only one person has primary accountability for any activity.
True
False
7.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Crashing is a project schedule compression technique that relies extensively on overlapping activities and a high degree of concurrency.
True
False
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Microsoft
or continue with
%20(1).png)
Apple
Others
Already have an account?