25-26 Earned Value Management PM1 Unit 5
Presentation
•
Business
•
9th - 12th Grade
•
Practice Problem
•
Easy
Bobbie Jones
Used 7+ times
FREE Resource
9 Slides • 16 Questions
1
Project Mgmt. 1
2
A metholody to measure progress and performance using 3 key numbers: PV, EV and AC
BAC (Budget At Completion) is simply the TOTAL Approved Budget!
PV The project's Planned Value (Total Budget point in time X % of completion)
EV The project's Earned Value (Current Work Complete % x Task Budget PV)
AC The project's Actual Cost (add all the money spent with receipts)
TCPI To Complete Performance Index (a ration or % of money needed to finish)
3
Givens will be EV, PV, and/or AC. (at least 2 must be given)
EVM Calculations about Money:
Cost Variance (CV);
Cost Performance Index (CPI)
EVM Calculations about Time:
Schedule Variance (SV);
Schedule Performance Index
Money Formulas:
CV=EV-AC
CPI=EV/AC
EVM Calculations about Time:
SV=EV-PV
SPI=EV/PV
Calculations You Will Make
4
The 4 Key EVM Calculations and Interpretations
5
Multiple Choice
A team has a budget of $1,500 that is 40% complete. During the 3-month timeline, the team planned to spend $500 each month. At the end of the FIRST MONTH, the team evaluates its progress. What is the planned value at this time?
Total Budget = $1,500
Timeline = 3 Months
$500
$1,000
$300
$600
6
Multiple Choice
Calculate a project's EV if Task Budget is $500 and the % Completion is 20% (EV actual complete times budget)
$25
$50
$100
$300
7
Memory Techniques
NOTE: All Variance (Difference) problems REQUIRE subtracting resulting in 0, more than 0 or less than 0
Variance Cost and Schedule Calculations
Cost Variance (CV) ~ CV=EV-AC
ScheduleVariance (SV) ~ SV=EV-PV
Children Eat Apples
Someone Else's Problem
8
Multiple Choice
The Planned Value (PV) for a project is $20,000, the Earned Value (EV) is $12,000, and the Actual Cost (AC) is $15,000.
What is the Cost Variance (CV)?
$5,000
$-3,000
$0
$3,000
9
Multiple Choice
The Planned Value (PV) for a project is $20,000, the Earned Value (EV) is $12,000, and the Actual Cost (AC) is $15,000.
What is the Schedule Variance (SV)?
$-8,000
$-5,000
$0
$3,000
10
Cost: A CV of $0 or More is on budget or over budget (We want a CV of $0 or higher)
Schedule: A SV of 0 or More is on schedule or ahead of schedule (we want a SV of 0 or higher)
Interpreting of SV and CV Results
11
Match
Match the following
SV= $12,000
CV = $-3,000
CV = $1,250
SV = $0
SV=$-5,000
Ahead of Schedule
Over Budget
Under Budget
On Schedule
Behind Schedule
Ahead of Schedule
Over Budget
Under Budget
On Schedule
Behind Schedule
12
Memory Techniques
NOTE: All Index(ratio) REQUIRE division result in 1, more 1, less 1
Performance Index Cost & Schedule Calculations
Cost Performance Index (CPI) ~ CPI=EV/AC Children Eat Apples
Schedule Performance Index (SPI) ~ CPI=EV/AC Someone Else's Problem
Children Eat Apples
Someone Else's Problem
13
Multiple Choice
A school is organizing a science fair with a total budget at completion of $10,000. The planned value at the end of week 3 is $7,000. They are 50% of the way through. This is an earned value of $5,000. Based on this information what is this project's SPI?
0.71
0.50
$-2,000
$-1,000
14
Multiple Choice
A school is organizing a science fair with a total budget at completion of $10,000. The planned value at the end of week 3 is $7,000. They are 50% of the way through. This is an earned value of $5,000. The team has spent $6000 so far. Based on this information what is this project's CPI?
$-2,000
0.71
0.83
$-1,000
15
Cost: A CPI of 1 or More On Budget or Under budget (we want 1 or more CPI)
Schedule: A SPI of 1 or More is On schedule or ahead of schedule
Interpreting of CPI and SPI Results
16
Match
Match the following
Earned Value Management (EVM)
Planned Value (PV)
Budget At Completion (BAC)
Earned Value (EV)
Actual Cost (AC)
Tracks progress using EV, PV and AC
Planned Completion % x Total Budget
Total budget approved for a project
Actual Completion % x Total Budget
Money that you have spent-receipt proof
Tracks progress using EV, PV and AC
Planned Completion % x Total Budget
Total budget approved for a project
Actual Completion % x Total Budget
Money that you have spent-receipt proof
17
Match
Match the following
CPI = 1.0
SPI = 0.85
CPI = 1.98
SPI = 1.0
SPI = 1.91
On Budget
Behind Schedule
Under Budget
On Schedule
Ahead of Schedule
On Budget
Behind Schedule
Under Budget
On Schedule
Ahead of Schedule
18
Earned Value Managment (Involves EV, PV, AC)
Good Outcomes are POSITIVE numbers and use words Under Budget and Ahead of Schedule.
When you calculate Variances You SUBTRACT! <=$0>= answers expected. Positive is good
When you calculate Indexes you DIVIDE! <=1>= answers expected.
19
Multiple Choice
A 7-day project has a total budget of $3,000. At the end of the 4th day, the project is 60% complete. What is the project's earned value at the end of the fourth day?
$1,200
$1,500
$1,800
$2,400
20
Drag and Drop
(List your answers in alphabetical order)
21
Drag and Drop
22
Drag and Drop
23
Drag and Drop
24
Drag and Drop
25
Drag and Drop
Project Mgmt. 1
Show answer
Auto Play
Slide 1 / 25
SLIDE
Similar Resources on Wayground
16 questions
Gas Laws Review (participation)
Presentation
•
10th - 12th Grade
19 questions
Unit 1: Friendship
Presentation
•
10th - 12th Grade
19 questions
Misc. SV Agreement
Presentation
•
9th - 11th Grade
18 questions
Gas Laws Lesson
Presentation
•
9th - 12th Grade
17 questions
BENTUK-BENTUK BADAN USAHA
Presentation
•
9th - 12th Grade
22 questions
Partial 2: GDP & SPI Activity
Presentation
•
9th - 12th Grade
22 questions
Ideal Gas Law
Presentation
•
9th - 12th Grade
22 questions
World War I Propaganda Poster Analysis
Presentation
•
9th - 11th Grade
Popular Resources on Wayground
10 questions
Safety Day 2026 – Student Review
Quiz
•
9th Grade
21 questions
Continents and Oceans
Quiz
•
6th Grade
20 questions
Parts of Speech
Quiz
•
5th Grade
16 questions
Subject & Predicate
Quiz
•
5th Grade
25 questions
Multiplication Facts
Quiz
•
5th Grade
12 questions
Map Skills
Quiz
•
3rd Grade
22 questions
Continents and Oceans
Quiz
•
5th Grade
15 questions
Rounding Decimals
Quiz
•
5th Grade
Discover more resources for Business
13 questions
BizInnovator Startup - Experience and Overview
Quiz
•
9th - 12th Grade
6 questions
Business of Retail - Chapter 4 The Retail Profit Model
Quiz
•
12th Grade
21 questions
UNIT 1-3 Review
Quiz
•
10th Grade
35 questions
Economics & Supply/Demand Review
Quiz
•
10th Grade
10 questions
BizInnovator Startup - What's Your Problem
Quiz
•
9th - 12th Grade