PM Unit 1
Flashcard
•
Other
•
12th Grade
•
Practice Problem
•
Hard
Wayground Content
FREE Resource
Student preview

47 questions
Show all answers
1.
FLASHCARD QUESTION
Front
Renovating a kitchen, planning a vacation, and starting a school club are all examples of:
Back
projects.
2.
FLASHCARD QUESTION
Front
Petrina sets up a timeline for the financial project she has been assigned. In her timeline, she includes benchmarks and milestones for her team to help keep the project on track. Petrina is establishing good project:
Back
time management.
3.
FLASHCARD QUESTION
Front
Andrew is the prom committee chairman. He is on-site at the prom to make sure all vendors show up at the event and all vendors' activities are falling within the scope of work contracted. Which process stage is Andrew in?
Back
executing
4.
FLASHCARD QUESTION
Front
A project can be defined as a:
Back
Temporary endeavor undertaken to create a unique product, service, or result
5.
FLASHCARD QUESTION
Front
Joe holds a team meeting to discuss lessons learned. He is in which process stage?
Back
closing
6.
FLASHCARD QUESTION
Front
Cheryl is watching the weather forecast for an outdoor senior picnic project that she planned to determine whether the picnic will need to be moved indoors. Which project process stage is Cheryl in?
Back
monitoring and controlling
7.
FLASHCARD QUESTION
Front
Andrew is the prom committee chairman. He is at the prom and realizes that the meal delivered to the attendees was steak and not chicken. Andrew makes the catering manager aware immediately that the chicken meal was agreed upon, so the steak meal is outside the project scope. Which project management process stage is Andrew in?
Back
monitoring and controlling
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?